Original plans called for simply renovating
the 29 West Main Street structure, but as work progressed
on upgrading Vigilant headquarters, the old building was
deemed unsalvageable, and construction crews began demolition
during the first half of November.
Once beyond that unexpected hurdle, the
fire company still plans on completing the $1.5 million
overhaul and expansion of the headquarters during the summer
of 2007.
Early in 2005, Vigilant announced plans
to refurbish a neighboring, former apartment building to
house emergency staff, provide administrative quarters and
serve as temporary housing for residents left homeless by
fires.
Project Architect Michael Proffitt stated
that the proposed expansion would increase the present structure
by about 820 square feet, and would involve refurbishing
much of the original structure, including dealing with a
bulging outer wall on the School Lane side.
He said the historic façade would
be maintained, but new stairs, an elevator and sprinklers
would be added to bring the structure into compliance with
safety standards.
As further evaluation of the old building
progressed during 2006, the planned overhaul got ugly.
John Damskey, vice president of the fire
company and chair of the buildings committee, recently told
The Dispatch, “We started out two and a half
years ago thinking we could remodel (the apartment building),”
but have since been advised “not to do it.”
He confirmed that the fire company would
be demolishing the structure completely. He said it had
been determined that the building had serious structural
problems, including a wall bulging out towards School Lane,
and that it would be a “better deal to demolish it”
than to attempt to save it.
Saving the front façade, as was originally
proposed, became hopeless after it was learned that the
bricks were crumbling. Damskey said, “We thought we
could save the front wall, but we ran into soft brick,”
and as a result of that discovery, the façade will
have to come down as well.
The fire company vice president stated that
an effort will be made to rebuild it “as close to
how it looked” before it was demolished.
The up side of the bad news is that the
demolition will permit the creation of a basement large
enough to provide a recreational and exercise area for company
personnel.
The remaining plans for use of the overhauled building remain
little changed. An elevator will be installed, as well as
staircases. The first floor of the new structure will serve
as offices, with the second floor serving as the “bunk”
area. The new attic when completed will be used for storage.
Damskey said, “We’re hoping
for the project to be completed during the summer 2007,”
but that it also dependent on what work can be accomplished
during the winter.