EMMITSBURG, Md. – The town could begin drawing down
money from an approved $656,107 community development block
grant (CDBG) this month.
The
town was awarded the grant in December 2005 to resolve both
a long history of sewage spills apparently originating from
a missing valve in the collection system, and to extend
sewer service to the new Emmitsburg Glass facility on Creamery
Road.
In
addition, the funds would be used to make modifications
at the sewer plant to accommodate improvements made along
the collection system itself.
Two
bids to begin the collection system work and glass company
site connection were approved at the Dec. 5 town meeting.
JHG
Contractors, Frederick, was awarded a bid of $67,945 to
begin work on the installation of a three-inch wastewater
forced main, as well as a bid of $114,000 for the installation
of an eight-inch water main.
Rejected
was a $735,105 bid from W. F. Delauter & Son, Thurmont,
for a forced wastewater main replacement and related work.
That bid represented a 163 percent increase over the estimated
cost of the project.
Work
on the approved projects, according to Town Manager David
Haller, could be completed in 90 to 100 days, although the
contracts would allow 240 days for completion. The work
could begin relatively soon, he said. Town spokeswoman Patricia
Feeser told The Dispatch work could begin during
the first week in February.
However,
proposed expenditures have to go through various levels
of state approval. The total grant amount is reserved for
the town at the state level, and the town will draw-down
on the allotment by submitting project-related bills as
work progresses.
Regarding
approval to spend money, Feeser said, “You have to
go through all the steps. There are environmental surveys
that have to be done, a lot of different steps.”
The
forced water main phase of the project, whose bid the commissioners
had rejected on Dec. 5, will be re-bid, but the papers to
do so have not yet been prepared.
The
wastewater collection system has been responsible for the
spillage of hundreds of thousands of gallons over the years,
the main culprit apparently being a missing valve which
may never have been installed. The valve would have acted
as a “brake” where the high-pressure wastewater
line coming from town met the gravity-feed line going to
the treatment plant.
The
proposed overhaul would remedy the spillage problem by switching
to an all-pressure collection system, and making adjustments
at the treatment plant to receive the high pressure inflow
of sewage.