EMMITSBURG,
Md. – In spite of heavy rains during the last week and
a half of June, changes made in the town’s wastewater
collection system are already paying off – no spills
in spite of the persistent deluge.
When
he saw that the area was to be hit with large amounts of
rainfall, Town Manager David Haller asked that work be speeded
up along a section of the wastewater collection system being
replaced through the Waybright property to the treatment
plant.
Even
though the treatment plant was subsequently hit with as
much as 1.9 million gallons in one day, the new line held
and the town got through its first major storms without
a sewage spill.
New
line held despite storms
Although
still compiling data from the more than a week of storms,
Haller said, that on Sunday, June 25 alone, the plant processed
1.9 million gallons of predominantly “wild water,”
well over the plant’s permitted 800-gallon-per-day
capacity.
During
the day, rainfall amounts ranged from 2.5 inches at the
treatment plant to 5 inches at the water treatment plant,
according to Haller.
Before
the storm front arrived on Friday, June 23, Haller had already
directed the construction crew working on the line and sewer
plant upgrade to cut the flow of sewage to a temporary by-pass
line and let it go through a new replacement line.
A by-pass
line had been installed so that workers could replace a
section of the old line that crosses the Waybright property
off Creamery Road, the source of sewage spills going back
decades.
Dealing
with potential ‘wastewater geysers’
The
main problem along the Waybright section of the line was
a missing valve which either never installed in a vault
in the 1980s when the system was constructed, or had been
subsequently removed.
Haller
had stated he felt that replacing this section of the line
would remedy 90 percent or more of the town’s sewage
spills. He chose to have an all-pressure line from the town
to the plant, eliminating the gravity-fed section, and the
need for a valve.
To
prevent wastewater geysers erupting at the treatment plant
because of the pressurized line, Haller had the wastewater
routed to the bottom of a partially filled tank. The water
already standing in the tank counteracts the force of the
pressurized wastewater coming into it and disperses the
energy.
Haller
said he expects the work on the system overhaul, including
treatment plant alterations, to be completed in 30-90 days,
depending on system testing.